Where does the handover usually break down in a phased hotel renovation?
I work on the supplier and project coordination side, and phased room renovations often become messy for a very ordinary reason: different teams use different room references. Operations may work by room number, purchasing by room type, and delivery records by package or revision. The physical work can be correct, but the handover still stalls because nobody can quickly confirm what belongs where, what has arrived, or who owns the final check.
A shared room map, revision label, staging zone and named sign-off owner can prevent a lot of confusion. For anyone who has worked through a live hotel renovation, where did the handover break down first?